Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Jump to:

Table of Contents
minLevel1
maxLevel6
outlinefalse
typeflat
separatorbrackets
printablefalse

PIs or technical leads of projects are requested to assemble their observing blocks as soon as possible by logging into the Observation Planning Tool (OPT) at https://apps.sarao.ac.za/opt/observations using the same credentials used for proposal submission.

Time allocation principles

The MeerKAT time allocation may seem a bit ambiguous due to the uncertainty in actual overheads. The following is intended to clarify the reasoning, and why you may be requested to adjust your submitted schedule blocks.

Overheads are considered to be the time spent on calibrators and slewing (i.e. any time not spent integrating on the science targets).  The percentage of overall requested time can vary based on the length of the schedule block, number of pointings and whether polarisation or other specialised calibration is needed, as described here: Observation overheads

The average observation overhead, considered across a full year of observing a varied science programme, works out to about 25%.  In order to ease the proposal preparation process, an overhead of 25% can be assumed when requesting time.  The total requested time on target is carefully considered during the feasibility and science reviews, and this is the key quantity in the time allocation.  Observers are requested to minimise overheads, when setting up their schedule blocks, and to adhere to the allocated integration times on target

For example, a proposal requested 8 hours on target, and assumed 25% overheads, leading to a maximum time request of 10 hours.  However, once the schedule block is set up and the observation is simulated, the total duration of the block is 9 hours.  This does not mean that the time on target should be increased to extend the block to 10 hours, since this is not necessary to achieve the science goal as per the approved project.  Conversely, we may have a situation where the observatory has requested the observer to split the observation into shorter blocks in order to expedite scheduling, and the overheads increase to 30% when following the recommended calibration strategy.  This would be considered acceptable in the cause of reducing scheduling idle time. 

The OPT

Instructions on using the OPT are here. JSON files generated earlier during proposal preparation may be uploaded to this interface. Please use your new assigned Project ID in the form SCI-YYYYMMDD-XX-nn or DDT-YYYYMMDD-XX-nn and not the ID issued by the proposal submission system. Should you encounter any difficulties please raise a support ticket here.

...

MeerKAT does not generate its observing schedule long in advance. Once your schedule block has been submitted, it will be checked by the Astronomer on Duty, and added to the queue. Please ensure that your start LST range is as flexible as possible to ease scheduling. Ensure your track length is less than six hours unless scientific considerations require a full track in one run. Long tracks (8+ hours) will be are more difficult to schedule so, if possible, we request that observers split their tracks in half - into two schedule blocks, selecting suitable LST start ranges for a ‘rising’ track and ‘setting’ track in order to maximise uv-coverage. However, this is not obligatory

Observation constraints

Observation constraints may be specified in the observation setup tab.

Users may use the ‘comments’ tab in the OPT to communicate constraints. Note that requests for night observations must be well motivated (generally at the proposal submission stage).

...

Note that due to disk storage constraints, data will be moved off active disk storage to tape after six months. Restaging data to disk is possible but may be subject to significant delays. You are therefore in any case advised to initiate transfer of your data as soon as possible to get started with reduction/analysis.

Due to the large volume of a typical imaging dataset, and the need to convert from MVF to MS format, the download link will may take up to 2 weeks to generate.

Data access

Calibration

OPT workflow

After your observation is completed